This material then passes through the suction pump and is discharged through the dredge discharge line, which is routed underwater to the east jetty. The terminal point for discharge of dredged material can be one of two areas -- a beach / surf zone pipeline or an offshore pipeline. These are chosen to best advantage of beach replenishment and odor control of decaying seaweed.
About the Suction HeadsThe dredge "Seabright" uses two types of suction heads to remove material from the bottom of the harbor and entrance channel.
In both cases, dredged material passes through the suction head and is discharged through the dredge discharge line. |